The client:Hilton Hotel at Heathrow Airport trusted hot tapping engineers, Ormond Pipework Services Ltd, to complete a live tapping on their commercial gas pipework. 

The problem:Hilton required a new branch off their existing gas installation to supply a new boiler. Downtime of the gas supply was not an option because the hotel was in use.

The only way to avoid downtime was to live tap the gas pipework. Ormond were brought in to perform a hot tapping in order to form the new branch. 

Our solution: Ormond welded a 3” on 10” hot tapping saddle to the existing pipework. 

After a successful pressure test, we began to under pressure drill the existing system. 

Once the live tapping was complete, a safety blank was attached to the valve. 

Hot tapping the connection avoided plant downtime, purging and testing.

 Tasks involved:

  • Hot tapping / Under pressure drilling on gas

  • Live tapping on steel pipework 

  • Pipe welding

We have used Ormond's hot tapping services for over 20 years, and will continue to do so

Richard Milner
South Yorkshire Mechanical, on behalf of Barnsley Hospital

Ormond Pipework made my job easy and I would highly recommend them

Anna Page
Great Bear Distributions

Ormond have done our hot tapping for the last 10 years, we trust them to always get the job done.

Jamie Griffin
Webber N.W Ltd Chief Engineer, on behalf of Jaguar Land Rover

Very professional. We choose Ormond every time for our pipework.

Pete Woodall
Smart Tec Solutions, on behalf of M&S

Our recent commercial gas engineering projects

View all projects →